|
Crested
Butte,
Colorado
– At the 19th
Annual Colorado Association of Stormwater and Floodplain Managers
conference held in Crested Butte, Colorado, September 10-12, 2008,
ICON Engineering, Inc. made
an entertaining presentation which incorporated a crowd pleasing video
starring an animated robot and one of ICON’s own engineers. The presentation was authored by
ICON’s own
Craig Jacobson, PE, CFM and
Steve Brown, PE, CFM. Entitled
“When Good Pipes Turn Bad – Evaluation and Inspection of a Major Pipe
Outfall System in Aurora, CO,” the presentation
focused on the results of
ICON
’s initial investigation and evaluation of a very large corrugated metal
pipe (CMP) outfall system. The purpose of this project was to evaluate the
existing hydraulic capacity and structural integrity of the existing storm
sewer system. The study also recommended immediate and future mitigation
or replacement needs. In order to accomplish the project tasks and goals,
new and innovative methods were utilized throughout the project during
analysis of the hydrology and pipe inspection, where a full line of
robotics testing was utilized to thoroughly document the internal
condition of the pipe system along with other forms of
“non-destructive” testing focusing on the various areas of concern.
The
City
Center
outfall system was
constructed in 1974 and ranges in size from 84-inches to 120-inches. The
overall length of the system is approximately 4,350 feet. The majority of
the pipe is CMP with a paved concrete invert. This pipe system serves as
the outfall for a large drainage basin within a very prominent area of the
City of Aurora. In fact, the pipe
system collects runoff from both the Aurora Mall
and the
Aurora Municipal Center
located adjacent to Alameda Avenue. Using SWMM to model the
hydrology, it was quickly identified that discharges had the potential to
exceed the system capacity. The pipe’s conveyance capacity was further
complicated by the complex interaction with the adjacent City Center
Detention Facility and at Alameda Avenue where the flows split
between the detention pond and outfall system are highly dependent on the
tailwater conditions. At the detention pond, the outfall system had the
potential to both convey water out of the pond, or “bubble-up” back
into the pond. Evaluation of these complex interactions surrounding the
outfall system required the development of a dynamic hydrology and storm
sewer model utilizing the EPA SWMM 5 program.
Three phases of testing were also completed on the outfall
pipe system to evaluate the current conditions and future integrity of the
pipes. First, a full line of testing utilizing a Responder Robotic
platform was completed to provide: Digital Fiber-Optic Closed Circuit TV
Reports (CCTV); Laser Scans for precision measurements of the internal
pipe shapes diameters, deformities, and deflections; and Gas Measurements
within the pipe. The second phase included comprehensive field inspection
and various “non-destructive” testing methods.
This testing focused on discolored and rusted areas that had the
potential to be detrimental to the structural integrity of the pipe.
Testing under this phase included: Visual inspection; Magnetic Particle
and Liquid Penetrant testing; Ultrasonic Measurements to determine wall
thicknesses; and Hardness measurements.
Finally, the third phase of testing included the removal and
inspection of small samples of CMP material, or “coupons”, in an
effort to determine the condition of the CMP material below the concrete
invert. Design of a
slip-lining is currently underway.
|

Corrosion above
the concrete invert of the 120-inch CMP City of Aurora City Center Storm
Sewer Outfall.

|