Timeline

Tentative Project Schedule

Notice to Proceed

July 2008

Draft Hydrology Report

October 2008

Final Hydrology Report

December 2008

Draft FHAD Report

January 2009

Final FHAD Report

March 2009

Draft Planning Report

May 2009

Final Planning Report

July 2009

 